[Construction Method]: Robotic Arm Vibration Method
[Pile Type Selected]: H-BZ-450-II, with a pile length of 12–15 meters.
Tonghu Town Beautiful Township and Beautiful Waterway Project
[Construction Method]: Robotic Arm Vibration Method
【Pile Type Selected】: H-BZ-300-Type I, pile length 6–9 meters.
Green Space and River Channel Remediation Project on Hejing Road, Liwan District, Guangzhou
[Construction Method]: Robotic Arm Vibration Method
【Pile Type Selected】: H-BZ-300-I (bark-imitation pile with color spraying), pile length 5 meters.
[Construction Method]: Robotic Arm Vibration Method
【Pile Type Selection】: H-BZ-300-Type I (bark-imitation pile), pile length 3–6 meters.
The hammering method is currently a widely used pile-driving technique.
Land piling
Mast-type rack + hydraulic impact hammer (16t-20t);
Pile driving on water
Marine pile-driving vessel + guide rod hammer (or hydraulic impact hammer)
Construction Method Advantages
High penetrating power, capable of adapting to geological conditions with relatively high N-values (≤30 blows).
Applicable scenarios
The suspended impact method is suitable for construction near water bodies where the engineering geology is relatively hard and a construction interface is available.
Construction Method Advantages
It has strong penetrating power and can adapt to geological conditions with higher N-values (≤25 blows). It can be suspended for construction over a certain distance and is also suitable for construction interfaces where there are significant elevation differences on site.
Applicable scenarios
This method is generally suitable for shore-side construction involving piles with smaller specifications and shorter lengths (≤12m), in areas with relatively soft engineering geology, and where a certain construction interface is available. When the N-value is relatively high, mechanical pilot drilling can be used to assist in pile driving.
Construction Method Advantages
Pile extraction, pile feeding, and pile driving are completed in one step, ensuring fast construction.
Management Project for the Yangmeizhou Section of the Xiangjiang River, a Major Tributary
[Construction Method]: Robotic Arm Vibration Method
【Pile Type Selected】: H-BZ-250-I, pile length 4–6 meters
[Construction Method]: Robotic Arm Vibration Method
【Pile Type Selected】: H-BZ-300-Type I, pile length 12 meters
[Construction Method]: Hammering Method + Floating Platform
[Pile Type Selected]: H-BZ-450-II, pile length 14 meters.
[Construction Method]: Excavator with vibratory hammer + mechanical pilot hole drilling (pilot hole first, then pile driving)
【Pile Type Selected】: H-BZ-450-II, pile length 12–14 meters.
Parking Facility Construction and Landscape Enhancement Project for Xinji Village, Mayong
[Construction Method]: Excavator with vibratory hammer + mechanical pilot hole drilling
[Pile Type Selected]: H-BZ-450-II, pile length 9 meters